TILENGA PROJECT ESIA REPORT

The ESIA Report for the Tilenga Feeder Pipeline Project has been prepared in accordance with the National Environment Act, and Environmental Impact Assessment Regulations (EIA), 1998.

The development of the ESIA Strategy for the Project was undertaken following discussions between the Project Proponents and the key Ugandan Regulators including National Environment Management Authority (NEMA) and Ministry of Energy and Mineral Development (MEMD). During the life of the Project, the Project Proponents will continually engage with relevant regulatory bodies including NEMA, the Petroleum Authority of Uganda (PAU), the Directorate of Water Resource Management (DWRM), National Forestry Authority (NFA), and others as necessary.

On behalf of the Project Proponents, TotalEnergies EP Uganda (TEPU) and the China National Offshore Oil Company Uganda Limited (CNOOC) the ESIA Report was prepared by independent NEMA registered Environmental Practitioners from RSK and Eco & Partner Consult.

The Project Proponents are committed to meeting best international practice for undertaking ESIA and thus the Project’s environmental and social performance will also meet the requirements of the International Finance Corporation (IFC) Performance Standards (PS) (2012). 

SEE DETAILED TILENGA PROJECT ESIA REPORT

Tilenga Feeder ESMP

This section describes how the mitigation measures identified in this environmental and social impact assessment (ESIA) will be implemented and monitored.

See more

Tilenga Feeder ESIA Introduction

This is an introduction to the Tilenga feeder pipeline environmental impact statement.

See more

Tilenga Feeder Pipeline ESIA: Sources of Cumulative Impact

Potential cumulative impact on groundwater around KP95, where the Tilenga feeder pipeline and the export pipeline converge at the manifold at EACOP’s PS1.

See more

Tilenga Feeder ESIA Alternatives

This section summarises the process undertaken during pre-front-end engineering design (design process before FEED) and FEED to evaluate the technically and financially feasible alternatives for the Tilenga feeder pipeline while taking into account environmental and social impacts.

See more

Tilenga Feeder ESIA Legislative

Tilenga Feeder Pipeline ESIA Section 4: Legislative, Policy and Administrative Framework, Permitting Requirements, and International Conventions, Standards, Guidelines and Agreements.

See more

ESIA process & method

The key steps of the Tilenga feeder pipeline ESIA process are illustrated in Figure 5.2-1, including steps through to pipeline implementation and the subsequent phase of reporting, audit and corrective actions.

See more

Environment & social baseline conditions

This section describes the existing environmental and social baseline conditions of the VECs for the Tilenga feeder pipeline.

See more

Tilenga Feeder Pipeline ESIA: Project description

This section describes the components of the Tilenga feeder pipeline associated with the Tilenga Project.

See more

Tilenga Feeder Pipeline ESIA: Stakeholder engagement

The term “stakeholder engagement” is a means of describing a broad, inclusive, and continuous process between a company and those potentially impacted that encompasses a range of activities and approaches and spans the entire life of a project (IFC 2007).

See more

Tilenga Feeder Pipeline ESIA Section 12: References

Tilenga Feeder Pipeline ESIA Section 12: References

See more

Tilenga Feeder Pipeline ESIA: Sources of Cumulative Impact

This presents the associated facilities that have been screened in to the cumulative impact assessment, and Table H1.2 shows the third-party developments that have been screened in to the cumulative impact assessment based on the criteria defined in Section 5 of the ESIA

See more

Tilenga Feeder ESIA CHA Summary

This Appendix provides an up-to-date summary of findings from the Critical Habitat Assessment (CHA) Interpretation carried out in 2017 (TBC & FFI 2017).

See more

Tilenga Feeder ESIA EACOP Standard

Subject to the regulatory requirements of Uganda and Tanzania and requirements of international lending institutions, environmental & social impact assessments, & stakeholder engagements have been implemented.

See more

Tilenga Feeder Pipeline ESIA - Executive summary

The environmental and social impact (ESIA) report is conducted to identify, describe and assess the likely interactions of the Tilenga feeder pipeline with environmental and socio-economic receptors, termed as “valued environmental and social components” (VECs).

See more

EA-1/EA-1A & EA-2 North Project – ESIA Scoping Report / Terms of Reference

The Environmental and Social Impact Assessment (ESIA) for the Exploration Area (EA) 1, 1A & EA-2 North Development Project commenced in May 2015 with AECOM as the lead consultant in partnership with Eco & Partner Consult as the local consultant. The project located in Buliisa and Nwoya Districts within Western Uganda. 

See more

TILENGA PROJECT ESIA- STAKEHOLDERS PRESENTATION

TEPU & TUOP recognized that the project must follow national and international best practices, like IFC Performance Standards requirements, in particular the requirement for the assessment of feasible alternative of the Project to respond to social & environmental characteristics of the Project area.
See more